6 Sigma Timeline
Posted by: Charles Posted on: Friday, 19th July 2002, 10:03 AM.
The general timeline is 3-6 months overall. Here's how I would break it down (in general) for a 6 month project:
Define: 1/2 month
Measure: 1 to 1.5 month
Analyze: 1 to 1.5 months
Improve: 2 months
Control: 1 month
If you don't have any data from the process, Measure takes longer. Sometimes Analyze can be done in a week if you have the right data. If not, you have to iterate back to Measure to gather the right data for segmentation or stratification purposes. Control can last longer if you need to run a pilot. Message Thread:  Return To Discussion ForumPost A New MessageRead the Forum Guide to Good Etiquette