Use a Modified FMEA to Mitigate Project Risks

Written by Arne Buthmann
Rate this item
(0 votes)
In order to prevent risks from happening, or at least to be prepared when they occur, team members should assess the key risks of any project and make a plan to address them. A FMEA chart is a helpful tool in tracking these risk-mitigation efforts.

By Arne Buthmann

Every project faces a number of elements that risk its success. For instance, a lack of team-member availability, qualified resources, customer information, data, proven technologies, a clear scope – or deficiencies in a number of these areas – represents a risk.

To prevent risks like these from happening, or at least to be prepared when they occur, project leaders and other team members should assess the key risks of any project and determine how they can be addressed.

One format and approach frequently used to complete this risk management is a “light” version of the common failure mode and effects analysis (FMEA). These four steps cover how to create a risk-mitigation plan. 

Step 1: Brainstorm Potential Project Risks and Potential Causes

In a meeting early in the process, the project team brainstorms and records potential risks. The leader guides this session with questions such as, “What can go wrong?” or “What might prevent this project from being successful?” These risks are recorded in a modified version of the FMEA (Figure 1).

Concerns from team members or other stakeholders also can be managed as risks. For example, if someone says, “We have tried to work on this issue before,” then the risk “solutions cannot be found” can be included in the project FMEA. This shows that the team members' concerns are taken seriously.

For each risk, the DMAIC phase during which it is most likely to occur is identified. Risks that are not specific to a phase can be assigned to the category "General."

The team also identifies potential causes for each risk. This will help to better determine corrective or preventive actions during Step 3.

Figure 1: "Light" Version of FMEA Risk Mitigation Plan

Step 2: Rate Potential Risks

Next, the team rates each risk according to its probability of occurrence and its impact on the project using the following categories:

  • 1 = low probability of occurrence, low impact on the project
  • 2 = medium probability of occurrence, medium impact on the project
  • 3 = high probability of occurrence, high impact on the project

The team discusses each risk until they reach consensus on its rating. Just because someone thinks a risk is a low probability (1), and another person assumes a high probability of occurrence (3), it is not correct to assign it a 2.

Step 3: Prioritize Risks and Define Mitigation Actions

Team members prioritize potential risks by calculating the product of the probability of occurrence and the impact on the project. They can create a traffic light scale to indicate which risks warrant mitigation actions and at what priority (Figure 2). The matrix will not be symmetrical because high-impact risks are considered more critical than risks with a high probability of occurring.

Figure 2: Risk Categorization Matrix

The team designs a plan for each risk in the yellow and red zones, including actions required to mitigate the risk, who is accountable and a due date.

Team members should always double check whether the actions are truly actionable and will really help to mitigate the impact or the probability of occurrence of the risk. In the best case, actions fully eliminate the risk. Second best are actions that reduce the probability of occurrence, while the third-best option is to define counter measures that work as a fall-back plan (i.e., if the team cannot prevent a risk from happening, they should still know what to do if it occurs).

Step 4: Continuously Update and Review Project-FMEA

Assessing risk is not a one-off activity. As the project moves forward, the team continuously updates the project FMEA and checks off the completion status of mitigation actions. An example of a chart at this stage is shown in Figure 3.

 Figure 3: Extract from Sample Project FMEA

The team assesses a new probability of occurrence for those risks that are adequately mitigated. Based on this rating, they can calculate and record a new risk status. The team also continues to identify new risks and addresses them as they arise. Deciding how and when new risks are to be addressed is best done during weekly status meetings.

About the Author: Arne Buthmann is a senior consultant with Valeocon Management Consulting in Europe. He has a wide range of experience in consulting and training multi-national usiness enterprises such as Novartis, Johnson & Johnson, Merial, Danone, TRW, Siemens and Bosch. Mr. Buthmann helps clients to implement Six Sigma, Lean and Design for Six Sigma. Mr. Buthmann's experience is in the areas of manufacturing, human resources, IT, purchasing, marketing and sales. He is a German national and can be reached at This e-mail address is being protected from spambots. You need JavaScript enabled to view it .

Additional Info

  • CID: 953

Add comment


From Our Partners

  
 
 
 
 
 
 
 
 


Training

Explore upcoming courses for Green Belt, Black Belt, Master Black Belt training and more. Plus, find out what certification
is all about.
More Training

Methodology

Learn about different approaches to process improvement.
The techniques can be used as part of a Lean Six Sigma
effort, or on their own. 
More Methodology

Implementation

Apply best practices to your process improvement effort, from launching Lean Six Sigma to taking it to the next level. 
More Implementation

Resources

Haven't found what you're looking for? Bookmark these spots
for fast access to top iSixSigma links. 
More Resources

Tools & Templates

Get the answers you need about the tools of the trade. Or, try
one of our templates or wizards to give you a jump start. 
More Tools & Templates

Featured Articles
Starwood Lean Six Sigma Team

Community: Starwood: No. 1 on Best Places to Work List
The 10 companies on iSixSigma's second annual Best Places to Work list have one thing in common: They have cultivated a winning work environment for their practitioners. At Starwood Hotels & Resorts, that environment includes a mix of opportunities for Belts.

Community: Welcome to the New iSixSigma.com
iSixSigma Publisher Katie Barry introduces the redesigned website and encourages readers to send feedback.

Implementation: Six Sigma Success Factors
To reap benefits, organizations must pay close attention to key factors that can make or break a Six Sigma deployment.

Community
chart

News: Florida Medical Center Uses Six Sigma to Improve Mortality Rate
Parrish Medical Center, a 210-bed community hospital in Titusville, Fla., has reduced mortality by 30.8 percent with help  from Thomson Reuters. The hospital also reduced "code blue" conditions — patients requiring resuscitation after a cardiac arrest or respiratory arrest — outside of the ICU by 76.5 percent.

Blogosphere: The People Behind Six Sigma Culture
Associate Editor Randy Woods blogs about the features in the March/April 2010 issue of iSixSigma Magazine, including an article on  iSixSigma's Best Places to Work and the seventh annual Global Salary Survey.

Blogosphere: Cox-Box Cartoon
See what Six Sigma Guy is up to in the latest cartoon, and visit the archives.

Events
chart

iSixSigma Live! Event: Energy Forum for Process Excellence - May 24-27      
In 2009, more than 150 process excellence leaders gathered in Houston for the 1st Annual Energy Forum for Process Excellence. In 2010, be sure you're a part of the 200 leaders who will learn and network with executives and practitioners across the energy sector.

Event: Webcast on New Lean Six Sigma Belt Certification Standard - March 10

iSixSigma Live! Event: 2010 DoD Performance Symposium - June 8-10

To learn about other upcoming public training sessions and conferences, visit the full events calendar.

Directory

The following guides – and many more designed to aid practitioners – are available in the Directory:

To find more resources, please visit the full Directory.