What Is Cpk?
 |
|
|
|
|
|
Message: 24152 Posted by: ScottS Posted on: Thursday, 27th February 2003
I thought that would get some attention...
Actually, where does the "k" come from. My best guess is that is is the initial of a guy named Kane who worte a paper on process capability indicies in '86.
Kane, Victor E. (1986). "Process Capability Indices," Journal of Quality Technology, vol. 18, no. 1, pp. 41-52.
Thanks for any info! Message: 24154 Posted by: Ross Posted on: Thursday, 27th February 2003
Hi Scott,
The "k" in Cpk is not for Victor Kane, although it would be a fitting tribute to his work in this field. The origins of k actually go back to the 1970s in Japan. The Japanese are credited with developing the the Cp, Cpl, Cpu, Cpk, and k indexes of process capability.
So what is k? It is an index of process centering, defined as follows, where M is the middle of the tolerance, mu is the process average, USL is the upper spec limit, and LSL is the lower spec limit:
k = |M - mu| / [(USL - LSL) / 2]
k is then used as follows to compute Cpk.
Cpk = Cp (1 - k)
When the process average is centered at the middle of the tolerance, M = mu, and therefore, M - mu = 0. With k = 0, Cpk will equal Cp.
Cpk = Cp (1 - 0) = Cp
If the process average is centered anywhere else, then the absolute value of the quantity M - mu is greater than zero, making k also greater than 0. Suppose k is 0.30 for a process. Then the Cpk index for this process is only 70% of the Cp index.
Cpk =Cp (1 - 0.30) = 0.70Cp
So in one way, k measures how much potential capability is lost due to poor centering. In the above example, Cpk could be increased by 30% if we could center mu at M.
Hope this helps.
Message: 24158 Posted by: jabavock Posted on: Thursday, 27th February 2003
k = katayori or kitayuri I'm not sure and it means the shift of process Message: 24161 Posted by: moly Posted on: Thursday, 27th February 2003
It should be "katayori" which means deviation, inclination or offset in my Japanese --> English Dictionary Message: 24175 Posted by: Gabriel Posted on: Friday, 28th February 2003
I have a booklet from Ford Motor Argentina "Control Continuo de Proceso" (i.e. Ongoing Process Control). It is dated 1983, it looks very much (both in content and in format) as the current SPC by AIAG, and I don't think it was "invented" by Ford Motor Argentina. It is probably based on a previous English version from Ford Motor Co. As a curiosity, this material does not even mention Cp, but it states "Cpk=MIN(USL-Xbarbar;Xbarbar-LSL)/3"
I am sure that Cpk is even much older than that, but this objective evidence is enough to prove that your theory is wrong.
Sorry, this does not answer your question.
Message: 24178 Posted by: Eileen Posted on: Friday, 28th February 2003
Scott,
You really started my day off with a good laugh. Vic and I worked together for many years. He would enjoy this one! He had nothing to do with defining the k in Cpk. Although his paper on Capability Indices is excellent, the index has been around for many decades. It can be found in some AT & T material from the 50's and 60's. I do not know where it originated. However, the definition of Cpk is frequently defined as:
Cpk = min 1/3(Zsub L, Z sub U)or min 1/3(lsl-xbar/sigma, usl-xbar/sigma)
The z-statistic is defined as (x-xbar)/sigma. This quantity used to be defined as the k-statistic in the 40's-50's, later to be changed to z. Hence, the Cpk. Maybe, we should change it to Cpz?
As for the Argentine Ford Material, it was originally written by Pete Jessup at Ford in North America, specifically Dearborn, Mich. Pete compiled existing material for the SPC manual. He did not define Cpk either. It is an index much older than either Vic or Pete.
Eileen Beachell, Quality Disciplines
Message: 24179 Posted by: ScottS Posted on: Friday, 28th February 2003
Thanks moly. That makes sense... After Ross's message, that is where I would have headed on my own. Thanks for the help. Message: 24182 Posted by: TMc Posted on: Friday, 28th February 2003
This may be a long shot, but in Mil Std 414, Inspection Sampling with varible data, you calculate the Qu and Ql and compare it to a k value. Mil Std 414 was replaced by ANSI/ASQ Z1.9
Message: 24183 Posted by: ScottS Posted on: Friday, 28th February 2003
jabavock and moly figured it out for me. Thanks all. Message: 93853 Posted by: duyen Posted on: Thursday, 18th May 2006
thank you Ross and Eileen, your answers really help, however what are the best values for cpk and cp? pls help. Do they need to be at center?
Message: 93921 Posted by: romel Posted on: Friday, 19th May 2006
If the item or the process is still in the design stage, target Cpk or Ppk must be 1.67 while for stable processes, it's 1.33.
There is a tendency that the data sampled is not in the center due to some variations/drifts and depending on the distance of the drift, this will further lessen the Cpk and will have larger defects
Message: 93963 Posted by: Pradeep Sharma Posted on: Saturday, 20th May 2006
Hi Romel,
Can i get in touch with you on your e-mail ID, need to understand how do we calculate CPk for process in design stage?
Pradeep Sharma
Message: 93974 Posted by: romel Posted on: Sunday, 21st May 2006
It's the same except that for design stage, Ppk or preliminary process capability is the term used and the target is 1.67. Also, the sample size may not be as big for the design stage and let the design team decide on this. Message: 97800 Posted by: Jamil Posted on: Tuesday, 25th July 2006
Hi all, I just a beginner in this spc, but i feel it is very interesting to explore a new things, wish you can help me. Message: 113079 Posted by: Eduardo Villarreal Posted on: Monday, 26th February 2007
Te envio la informacion de porque es la K en CPK.
saludos.
Message: 128431 Posted by: Jose Posted on: Friday, 12th October 2007
After reading all the responses, nobody has been able to explain what K means. Why K instead of S or W????
Why we look at Japanese words to find the answer to this question?
The answer may simply be that somebody selected K to describe the offset location of the mean. Plain and simple/
Thoughts please.
Message: 128432 Posted by: Chad Vader Posted on: Friday, 12th October 2007
Jose
Why do you care.................
Copyright © 2000-2008 iSixSigma All Rights Reserved Reproduction Without Permission Is Strictly Prohibited Copyright Requests
Publish an Article: Do you have a Six Sigma tip, learning or case study? Share it with the largest community of Six Sigma professionals, and be recognized by your peers. It's a great way to promote your expertise and/or build your resume. Read more about submitting an article.
"The Bottom Line" Links
|
|
|
|
1BMG
UNIVERSITY.
|
I
I
|
|
I
I
|
• Reduce Travel Costs
• Maximize Training Budget
|
|
![]() |
|
|
![]() |
|
SIGMAPRO |
MBB, Lean Sigma, & DFSS
when
experience
matters
most...
|
|
![]() |
M O T O R O L A U N I V E R S I T Y |
Learn from the most experienced practitioners of Six Sigma in the world
Public Training & Certification
Click here to take a free Six Sigma Lesson
|
|
![]() |
|
J |
URΛN
| |
Lean Six Sigma Public Workshop
Upgrade to Black Belt - November 2008
Become one of your organization's 'vital few'. Get Juran Certified. |
|
|
![]() |
Pyzdek
Institute |
Online training and certification
from the author of the
Six Sigma Handbook |
Starting at
$695 |
|
![]() |
|
LodeStar Institute
| |
Affordable DFSS, Lean Sigma, MBB
Public & On-site Certifications |
|
On-site
certification classes starting from $1,800/person!
>>Learn about LSI
specials... |
|
![]() |
Finding that key person for your team is just a click away . . .
|
|
|
TheJobShop
jobs.isixsigma.com
|
|
|
|
|
|
![]() |
THE UNIVERSITY OF
TEXAS
AT AUSTIN |
|
2 weeks + 1 project = Black Belt Certification
|
|
|
![]() |
| . |
Find us on LinkedIn |
Join the iSixSigma Network and Connect with Other Six Sigma Pros |
|
| . |
|
![]() |
| . |
iSixSigma Live! Summit & Awards Jan 13-16, 2009 • Miami, FL |
Save up to $500 • Click Here! Register by October 14 |
|
| . |
|
Download the iSixSigma Toolbar for 1-Click access. Search Your Way. Everyday. Without Delay.

|
 |
|