    You could get the team members with the spread of variation (high Low) in a room after your Gemba visit and facilitate them to complete a Metric Based Process Map – in each step record the process tie, lead time, % complete and Accurate- Google Karen Martin MBPM Im not very experienced but find this tool very useful. And the team will be more likely to stay with a process if they have developed it.

    Good luck

    0
    #236465

    Charlie Tindill
    Participant

    Some good advice Mike, not being very experienced myself, ill take a look Thank you – Charlie