iSixSigma

Sebvlarsen

Forum Replies Created

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #243502

    Sebvlarsen
    Participant

    Hi again,

    I have looked through all the topics now, but it still deosnt make sense with the project im working on.

    My main Six Sigma goal os to improve on delivery time of orders being sent.

    I have collected data from 1000 orders, whereas 512 of them were delivered too late (later than 5 days).

    i also have the top 5 reasons for these.

     

    But how do i do an MSA for this kind of data?

    0
    #243501

    Sebvlarsen
    Participant

    Hi,

    I did not see these, thank you!

    i will take a look.

    0
Viewing 2 posts - 1 through 2 (of 2 total)