    Hello.I do my thesis in 6sigma and have some data from a ceramic tiles company.This company has 1 production line where (according to the production plan) something like 70 product lines are being produced.I did a pareto and most of the lines contribute the same to the overall defectives.In the end of the line, there is an optical then a dimensional and then a control of the even surface.The product is either categorised as defective by the first second or third control.U cannot know if a product is defective by more than one controls.So lets sau i have overal 100.000 ceramic tiles being prodiced (not categorized by product line) and have something like 6.000 defectives from optical control,3.000 from dimensional 3.000 from even control.How do i calculate the sigma level?
    1. Yield=88%-Sigma=1,5 (the classical way)
    2. a) DPU=Yield (since i cannot categorize defects and for me 1 defective=1 defect?)and therefore sigma level=2,7? Or i convert yield to dpu RTY=e^(-DPU) and then from Sigma level = 0.8406 +sqrt(29.37-2.221 * ln (ppm) formula sigma=2,7?
    3.Its is a compound product so i dont think i have to use DPMO.Anyway,as an opportunity i consider 3 and DPMO=(120000/3(13.0000))*1000000 Sigma level almost 3,2!!!
    Moreover the distribution of the average defects per month (N=11 months) has ?=0,87 but StDev=0,03!!Is there any connection with the above sigma levels (although i know they conclude the supposed 1,5? drift)??plz Help!!Which one of them should i use

    Additionaly, I am trying to evaluate the indices of the specific weight in pulp mills used in athe ceramic tiles company. The mills are used randomly and the company keeps data of the specific weight in not fixed time but when a mill is going to empty.Is that safe to use Capability indices when my process in not inherently normal?And after i transform it to normal shouldnt Pp almost equal to Cp and even Cp
    Huge post but ypur answer would be more than helpful.Thank you

    #176154 Reply

    Additionaly, I am trying to evaluate the indices of the specific weight in pulp mills used in athe ceramic tiles company

    #176220 Reply

    Do you understand the difference between defects and defectives?

    #677818 Reply

    ali

    hi, i work in qc ceramic tile whit 4 line product. more important defect in our company is Superficial defect like pinhoul in product. planning is second and liner is last because of chamfering.

Viewing 4 posts - 1 through 4 (of 4 total)

Register Now

  • Stop this in-your-face notice
  • Reserve your username
  • Follow people you like, learn from
  • Extend your profile
  • Gain reputation for your contributions
  • No annoying captchas across site
And much more! C'mon, register now.

Reply To: Calculation of Sigma level and Indices in Ceramic Tiles Company
Your information:






5S and Lean eBooks
GAGEpack for Quality Assurance
Six Sigma Statistical and Graphical Analysis with SigmaXL
Six Sigma Online Certification: White, Yellow, Green and Black Belt
Lean and Six Sigma Project Examples
Six Sigma Online Certification: White, Yellow, Green and Black Belt

Find the Perfect Six Sigma Job

Login Form