    The Leadership Council has suddenly placed a constraint in the pre pilot phase that was not there before. Providing “floor-space” for a solution that is key to solve the root cause is being denied.What to do now?

    0
    #127355

    jimmie65
    Participant

    1) Find another solution.
    Or 2) Make a business-case argument for the floor space.
    Or 3) Find some other areas you can siphon floor space from with Lean tools.
    Or 4) Figure out a way to implement your solution in less floor space.
    Or 5) Get fed-up with management sabotaging your projects, turn in your resignation, and find another job.