iSixSigma

Question about PPM Cpk…

Six Sigma – iSixSigma Forums Old Forums General Question about PPM Cpk…

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #33534

    Omar Olazaran
    Participant

    What is the relationship between the PPM and Cpk ???
    Thanks !!!
    Omar Olazaran

    0
    #90930

    Logan
    Participant

    Process Sigma = NORMSINV(1-((Total Defects) / (Total Opportunities))) + 1.5Cpk=Process Sigma / 3Before doing such a conversion, please make sure two things:1) Process is stable/under control2) Samples were collected randomly

    0