iSixSigma

Value Stream Mapping

Six Sigma – iSixSigma Forums Old Forums General Value Stream Mapping

This topic contains 4 replies, has 5 voices, and was last updated by  gscom 11 years, 8 months ago.

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #46309

    Neo
    Participant

    Hi everyone,
    I am doing a current state value stream map and I’m wondering if Processing Lead Time should include the rework process time or should it be included under the Total Processing time. My thouht is that it would not be included in the Process Lead Time but under the Total Processing Time.
    Any advise would be greatly appreciated.
    Thanks

    0
    #152796

    Ovidiu Contras
    Participant

    Neo,
    You’re correct – with the mention – you have to capture somewhow the information about rework (x% rework) next to the operation. VSM is an excellent tool to capture waste, and rework is waste.
    Hope this helps

    0
    #152805

    BritW
    Participant

    You are correct. If you include it in total lead time, then it will show up as a waste value.  Reducing rework will reduce waste and then your overall total lead time.

    0
    #152809

    The Force
    Member

    You can include the rework time in the processing time but under that process, identify a metric which pertains to rework (e.g. first time through, OEE, rework rate, others) or use a quality filter mapping tool.

    0
    #164166

    gscom
    Participant

    If your rework is standard and has a percentage of the total work, it would be included in the process time of the reworked process. if added to the total process time may give a fauls impression of the total process time. (in my opinion)

    0
Viewing 5 posts - 1 through 5 (of 5 total)