iSixSigma

WB DMAIC Project on MSA?

Six Sigma – iSixSigma Forums General Forums Methodology WB DMAIC Project on MSA?

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #55231

    Bose
    Participant

    I am coaching a WB DMAIC project. The project is in Measure phase. MSA(CEM) used for measuring dairy butter fat has lot of variation. In a study, Gage R&R is 80%. By fixing the MSA system will possibly save huge. Can a DMAIC project be done on a MSA itself?

    0
    #199277

    Norbert Feher
    Participant

    Well, technically yes but practically as a Six Sigma mentor I would ask for a sustained improvement becasue Six Sigma is about process improvement and not measurement system development. (of course the latter is necessary to achieve the first one)

    Sorry :-(

    0
    #199279

    Chris Seider
    Participant

    I would make sure you find a secondary metric that shows the financial impact of improving the gage.

    Do cycle times reduce, do on-time deliveries improve, does demurrage reduce, etc. Add a secondary metric and of course your project champion can best help out with that.

    0
    #199285

    Arun sathish RS
    Participant

    It is like Just do Projects

    0
    #199292

    Kurry
    Participant

    Yes,DMAIC project can be used for %GRR improvment.I see in a study your %GRR is 80%,that can’t be accecptable and your measuring system is not ok,you need better measuring system to make sure dairy butter fat rate is under control.thanks.

    0
Viewing 5 posts - 1 through 5 (of 5 total)